|
| December |
 |
The Extra Vehicular Activity (EVA) and Crew Systems
Office supported meetings at JSC for Return-to-Flight efforts
for future EVA enhancements (such as rigid handrails, soft handrails,
and foot restraints).
Vacuum acquisition on the WFC3 flight infrared detector has
been successfully completed. The detector has successfully undergone
continuity and warm functional testing.
The WFC3 infrared flight detector baffle and shield were aligned,
detector continuity testing was completed, and the detector
housing assembly has successfully passed vacuum leak testing.
The detector process flow is continuing.

|
| November |
 |
The WFC3 flight Ultraviolet Visible (UVIS) detector #1 Pre-ship
Review was successfully completed at Ball Aerospace.
The WFC3 development program completed a significant milestone
with the successful execution of the initial functional test
of the fully integrated instrument. Both the Infrared and Ultraviolet
Visible channels, utilizing the surrogate detectors, produced
quality images.
The WFC3 UVIS flight detector 1 has completed its final functional
test and alignment check.

|
| October |
 |
Functional testing of the WFC3 UVIS flight spare detector
was successfully completed.
The WFC3 flight Infrared detector wire weld repair has been
completed. All of the other wire welds were visually inspected
under magnification.

|
| September |
 |
The WFC3 flight Ultraviolet Visible (UVIS) detector
#1 Pre-ship Review was successfully completed at Ball Aerospace.
The WFC3 development program completed a significant milestone
with the successful execution of the initial functional test
of the fully integrated instrument. Both the Infrared and Ultraviolet
Visible channels, utilizing the surrogate detectors, produced
quality images.
The WFC3 UVIS flight detector 1 has completed its final functional
test and alignment check.

|
| August |
 |
The WFC3 UVIS flight detector 1 is undergoing its final
thermal testing. After thermal testing is completed, functional
testing will be performed, followed by post-vibe alignment verification.
The WFC3 UVIS Gas Charge Heat Pipe thermal vacuum testing has
commenced. Testing ran through the week.
The WFC3 flight UVIS detector assembly has been aligned and
staked and is undergoing functional testing.

|
| July |
 |
WFC3 UVIS Flight Detector has completed 3 of 4 planned
thermal cycles without issue. The final cycle is scheduled for
this week.
The WFC3 Infrared (IR) flight detector ghost baffles were successfully
assembled and aligned on the IR detector assembly.
The WFC3 Ultra-violet Visible (UVIS) flight detector assembly
is undergoing thermal cycling at Ball. Alignment activities
will continue after completion of thermal cycling.

|
| June |
 |
WFC3 post vibration encircled energy testing has been
successfully completed. Preliminary analysis of the results
shows that both channels are well within their alignment budgets.
The WFC3 Optical Assembly has been installed in the Radial
Instrument Alignment Fixture and post vibration Encircled Energy
testing has begun on the UVIS channel.

|
| May |
 |
The WFC3 Science Oversight Committee (SOC) met Thursday
at the STScI. The SOC was pleased with the progress of the instrument
and commended the WFC3 team's performance.
The WFC3 Optical Assembly was reinstalled into the Flight Enclosure
in preparation for post vibration encircled energy testing.
The flight WFC3 UVIS Detector Assembly 1 has been reassembled
following repair of the 2-stage thermo electric cooler to S-strap
interface.
Main electronic boxes (MEB) 1 and 2, the blind mate connector,
the low voltage power supply (LVPS), the remote interface units
and expander units, detector electronics filters, 4 heater controllers,
the MEB heat pipes, and the radiator trusses have all been installed
onto the flight enclosure.

|
| April |
 |
Optical testing of the WFC3 at GSFC is continuing.
During this testing, the Space Telescope Science Institute (STScI)
has obtained more than 3,000 images with both the UVIS and IR
channels of WFC3. The STScI has also performed quick look analysis
and has started a more detailed analysis of the data. The data
will provide a pre-vibration test baseline for the WFC3 configuration
and will be used to derive the best focus of both channels.
The WFC3 flight CCD Electronics Box (CEB) and the calibration
lamp assembly have both successfully completed vibration testing.
The WFC3 Science Oversight Committee approved Infrared (IR)
detector Focal Plane Assembly 64 for use. The detector was hand
carried to Ball this week to begin integration into the first
flight IR detector assembly.

|
| March |
 |
The first images from the IR channel were taken and
the first set of IR phase retrieval images has been successfully
completed.
Life testing on the WFC3 Engineering Unit IR Filter Wheel assembly
has successfully completed its first life cycle, which is equivalent
to the number of operations that it would see over its expected
lifetime.

|
| February |
 |
The WFC3 Pick Off Mirror (POM) was installed onto the
WFC3 Optical Assembly
Recently delivered WFC3 Infrared detectors have demonstrated
significantly superior results compared to previous lots.
The WFC3 Optical Assembly was removed and reinstalled in the
flight enclosure to verify repeatability prior to vibration
testing.

|
| January |
 |
Metrology of the WFC3 optical assembly installed within
the flight enclosure has been completed.
the WFC3 Flight Thermo-Electric Coolers for IR Electronics
(TECFIRE) units have successfully completed vibration testing
and bake-out.
The WFC3 flight Pick-Off Mirror (POM) has been received at
GSFC from Ball, and has successfully undergone receiving inspection.
The WFC3 Optical Assembly has successfully completed post delivery
inspection, mass properties measurement, and has been installed
into the enclosure.

|
|