Documents - Reviews

Review Timeline

All NASA instrument projects have a standard protocol of reviews that occur during the course of building the instrument (see timeline). Below are excerpts from the two main reviews that have occurred so far. The Flight Readiness Review (FRR) is forthcoming.

On October 31, 2006, NASA Administrator Mike Griffin announced that there will be another servicing mission (SM4) to Hubble to be launched in mid- to late-2008. Read NASA Press Release

2000 Dec :: Critical Design Review (CDR)

  • Configuration Overview
    A 14 pg summary of the different parts of WFC3 and its installation into Hubble.
    Download: PDF (13.2 Mb) or PowerPoint (4.3 Mb)
  • Science Overview
    A 27 pg summary of the science and astronomy that WFC3 would be optimal for.
    Download: PDF (4.9 Mb) or PowerPoint (2.2 Mb)

1999-2000 :: Preliminary Design Review (PDR)

  • Science Instrument Overview
    A 24 pg summary of the components and capabilities of the WFC3 instrument.
    Download: PDF (10.0 Mb) or PowerPoint (2.8 Mb)